Hermes test reactor

also Hermes 1, Hermes Low-Power Demonstration Reactor

Kairos Power's 35 MWt non-power test reactor in Oak Ridge, Tennessee, cooled by molten fluoride salt with solid TRISO fuel. NRC construction permit CPTR-6 (2023); safety-related construction began May 2025. It will not generate electricity.

Operator
Kairos Power
Type
Research reactor
Approach
FHR
Fuel
TRISO, HALEU
Country
US
Status
Under construction

Design values

What the machine was built to do, as published. Not results, and never ranked.

Design values for Hermes test reactor
ParameterValueUnit StatusSource
Thermal capacity (rated) medium confidence 35 MW MW planned Kairos Power (Wikipedia) aggregator